RISWIS Core Banking System - Task Breakdown & Implementation Plan

Version: 1.0 Date: January 2025 Document Owner: RISWIS Development Team Status: Implementation Ready


Table of Contents


Executive Summary

This document outlines the comprehensive task breakdown for completing and deploying the RISWIS core banking system. Based on extensive codebase analysis, the system is approximately 85% complete with a solid foundation requiring focused effort on customer-facing applications, advanced integrations, and market deployment.

Current System Status

  • Core Banking Engine: 95% complete

  • Internal Staff Applications: 90% complete

  • Transaction Processing: 95% complete

  • Loan Management: 90% complete

  • Risk Management: 85% complete

  • ⚠️ Customer-Facing Apps: 15% complete

  • ⚠️ External Integrations: 40% complete

  • ⚠️ Production Deployment: 60% complete

Timeline Overview

  • Phase 1: 2-3 months (Core completion)

  • Phase 2: 3-4 months (Customer applications)

  • Phase 3: 2-3 months (Integrations)

  • Phase 4: 1-2 months (Market deployment)

  • Total Duration: 8-12 months to full market readiness


Project Phases Overview

Phase 1: Core System Completion (Months 1-3)

Objective: Complete remaining core banking functionality and stabilize the platform

Key Deliverables:

  • Customer mobile banking application

  • Internet banking portal

  • Advanced reporting modules

  • System performance optimization

  • Security hardening

Phase 2: Customer-Facing Applications (Months 4-7)

Objective: Develop comprehensive customer self-service capabilities

Key Deliverables:

  • Mobile banking app (iOS/Android)

  • Web banking portal

  • USSD banking integration

  • Customer onboarding portal

  • Self-service features

Phase 3: Advanced Integrations (Months 8-10)

Objective: Integrate with external payment systems and regulatory platforms

Key Deliverables:

  • Payment gateway integration

  • Mobile money connectivity

  • Central Bank reporting

  • Credit bureau integration

  • International remittance systems

Phase 4: Market Deployment (Months 11-12)

Objective: Deploy to production and onboard pilot customers

Key Deliverables:

  • Production infrastructure setup

  • Pilot bank implementation

  • Staff training programs

  • Go-live support

  • Post-deployment optimization


Phase 1: Core System Completion

1.1 Backend API Completion

Task 1.1.1: Complete Missing API Endpoints

Priority: HIGH Effort: 2 weeks Assignee: Backend Developer

Subtasks:

Acceptance Criteria:

  • All API endpoints documented in OpenAPI spec

  • 100% test coverage for new endpoints

  • Performance benchmarks met (<500ms response time)

  • Security review completed

Task 1.1.2: Database Optimization

Priority: HIGH Effort: 1 week Assignee: Database Administrator

Subtasks:

Acceptance Criteria:

  • Query performance improved by 50%

  • Database monitoring dashboard operational

  • Backup verification automated

  • Connection pooling optimized

Task 1.1.3: Error Handling & Logging Enhancement

Priority: MEDIUM Effort: 1 week Assignee: Backend Developer

Subtasks:

Acceptance Criteria:

  • Consistent error handling across all endpoints

  • Structured logs with searchable metadata

  • Error alerting configured for critical issues

  • API documentation includes error scenarios

1.2 Frontend Core Completion

Task 1.2.1: Mobile Responsiveness Optimization

Priority: HIGH Effort: 2 weeks Assignee: Frontend Developer

Subtasks:

Acceptance Criteria:

  • All pages responsive on devices 320px+

  • Touch-friendly interface elements (44px+ touch targets)

  • Offline functionality for transaction viewing

  • PWA installable on mobile devices

  • Performance score >90 on mobile

Task 1.2.2: Advanced Dashboard Components

Priority: MEDIUM Effort: 2 weeks Assignee: Frontend Developer

Subtasks:

Acceptance Criteria:

  • Interactive charts and graphs functional

  • Real-time data updates via WebSocket

  • Advanced filtering saves user preferences

  • Dashboard customization persists across sessions

  • Data export functionality working

Task 1.2.3: User Experience Improvements

Priority: MEDIUM Effort: 1 week Assignee: UI/UX Developer

Subtasks:

Acceptance Criteria:

  • Loading states visible for operations >500ms

  • Clear feedback for all user actions

  • Intuitive navigation with breadcrumbs

  • Keyboard shortcuts documented and functional

  • Bulk operations work for common tasks

1.3 Security & Compliance Hardening

Task 1.3.1: Security Audit & Penetration Testing

Priority: HIGH Effort: 2 weeks Assignee: Security Specialist

Subtasks:

Acceptance Criteria:

  • Zero critical security vulnerabilities

  • Security audit report completed

  • OWASP Top 10 compliance verified

  • Security monitoring alerts configured

  • Security documentation updated

Task 1.3.2: Compliance Framework Implementation

Priority: HIGH Effort: 3 weeks Assignee: Compliance Developer

Subtasks:

Acceptance Criteria:

  • AML screening integrated with customer onboarding

  • CBL reports generated automatically

  • Complete audit trails for all transactions

  • Data retention policies enforced

  • Compliance dashboard shows all metrics

1.4 Performance Optimization

Task 1.4.1: Backend Performance Tuning

Priority: HIGH Effort: 2 weeks Assignee: Performance Engineer

Subtasks:

Acceptance Criteria:

  • API response times <500ms for 95% of requests

  • Database query times optimized

  • Rate limiting prevents abuse

  • Performance monitoring dashboard operational

  • Load testing passes for 1000 concurrent users

Task 1.4.2: Frontend Performance Optimization

Priority: MEDIUM Effort: 1 week Assignee: Frontend Developer

Subtasks:

Acceptance Criteria:

  • Initial page load <3 seconds

  • Bundle sizes optimized (main bundle <500KB)

  • Service worker caches static assets

  • Images optimized and responsive

  • Core Web Vitals scores >90


Phase 2: Customer-Facing Applications

2.1 Mobile Banking Application

Task 2.1.1: Mobile App Foundation

Priority: HIGH Effort: 4 weeks Assignee: Mobile Developer

Subtasks:

Acceptance Criteria:

  • React Native app runs on iOS and Android

  • Biometric authentication (Face ID/Touch ID)

  • Core UI components match design system

  • Offline mode for account viewing

  • Push notifications functional

Task 2.1.2: Core Banking Features

Priority: HIGH Effort: 6 weeks Assignee: Mobile Developer

Subtasks:

Acceptance Criteria:

  • Real-time balance updates

  • Secure fund transfers with confirmations

  • Bill payment integration working

  • Loan application workflow complete

  • In-app customer support functional

Task 2.1.3: Advanced Mobile Features

Priority: MEDIUM Effort: 3 weeks Assignee: Mobile Developer

Subtasks:

Acceptance Criteria:

  • QR code generation and scanning functional

  • Mobile money transfers working

  • Spending analytics with visualizations

  • ATM/branch locator functional

  • Document scanning with OCR

2.2 Internet Banking Portal

Task 2.2.1: Web Banking Foundation

Priority: HIGH Effort: 3 weeks Assignee: Frontend Developer

Subtasks:

Acceptance Criteria:

  • Separate customer web application

  • Multi-factor authentication required

  • Responsive dashboard for all devices

  • Secure session management

  • Profile management with KYC updates

Task 2.2.2: Banking Operations Interface

Priority: HIGH Effort: 4 weeks Assignee: Frontend Developer

Subtasks:

Acceptance Criteria:

  • Complete account overview and details

  • Advanced transaction search and filtering

  • Secure fund transfer with confirmations

  • PDF statement generation and download

  • Loan application and status tracking

Task 2.2.3: Customer Self-Service Features

Priority: MEDIUM Effort: 2 weeks Assignee: Frontend Developer

Subtasks:

Acceptance Criteria:

  • Service requests tracked to resolution

  • Online appointment booking functional

  • Feedback system with ratings

  • Secure document upload and storage

  • Basic financial planning calculators

2.3 USSD Banking Integration

Task 2.3.1: USSD Gateway Integration

Priority: HIGH Effort: 3 weeks Assignee: Integration Developer

Subtasks:

Acceptance Criteria:

  • USSD codes functional on all networks

  • Session management prevents timeouts

  • Intuitive menu navigation

  • Secure transaction processing

  • PIN-based authentication working

Task 2.3.2: USSD Banking Features

Priority: MEDIUM Effort: 2 weeks Assignee: Integration Developer

Subtasks:

Acceptance Criteria:

  • Real-time balance inquiry

  • Transaction history via USSD

  • Fund transfers with confirmations

  • Bill payment integration

  • Loan information accessible


Phase 3: Advanced Integrations

3.1 Payment Gateway Integration

Task 3.1.1: Card Processing Integration

Priority: HIGH Effort: 4 weeks Assignee: Integration Developer

Subtasks:

Acceptance Criteria:

  • Card payments processed successfully

  • PCI DSS compliance certified

  • Real-time authorization and settlement

  • Card blocking/unblocking functional

  • Fraud detection alerts working

Task 3.1.2: Online Payment Gateway

Priority: HIGH Effort: 3 weeks Assignee: Integration Developer

Subtasks:

Acceptance Criteria:

  • Online payments processed securely

  • 3D Secure authentication functional

  • Recurring payments automated

  • Payment reconciliation accurate

  • Refund processing working

3.2 Mobile Money Integration

Task 3.2.1: MTN MoMo Integration

Priority: HIGH Effort: 3 weeks Assignee: Integration Developer

Subtasks:

Acceptance Criteria:

  • MTN MoMo accounts linked successfully

  • Bi-directional money transfers working

  • Real-time balance updates

  • Transaction reconciliation automated

  • Error handling for failed transactions

Task 3.2.2: Orange Money Integration

Priority: HIGH Effort: 3 weeks Assignee: Integration Developer

Subtasks:

Acceptance Criteria:

  • Orange Money integration functional

  • Account verification working

  • Transfer and payment processing

  • Real-time transaction monitoring

  • Webhook notifications handled

3.3 Regulatory & Compliance Integrations

Task 3.3.1: Central Bank of Liberia Integration

Priority: HIGH Effort: 4 weeks Assignee: Compliance Developer

Subtasks:

Acceptance Criteria:

  • CBL reports generated automatically

  • Regulatory data collected accurately

  • Report generation scheduled

  • Compliance violations detected

  • Filing system tracks submissions

Task 3.3.2: Credit Bureau Integration

Priority: MEDIUM Effort: 3 weeks Assignee: Integration Developer

Subtasks:

Acceptance Criteria:

  • Credit scores retrieved in real-time

  • Credit history accurate and current

  • Automated screening for loan applications

  • Regular data synchronization

  • Credit reporting compliance maintained


Phase 4: Market Deployment

4.1 Production Infrastructure Setup

Task 4.1.1: Cloud Infrastructure Deployment

Priority: HIGH Effort: 3 weeks Assignee: DevOps Engineer

Subtasks:

Acceptance Criteria:

  • Production environment operational

  • Load balancing distributes traffic

  • Database cluster provides high availability

  • Monitoring covers all system components

  • Disaster recovery tested and documented

Task 4.1.2: Security & Compliance Setup

Priority: HIGH Effort: 2 weeks Assignee: Security Engineer

Subtasks:

Acceptance Criteria:

  • Security controls operational

  • Intrusion detection alerts configured

  • Audit logs captured and stored

  • Data encrypted at rest and in transit

  • Compliance monitoring automated

4.2 Pilot Implementation

Task 4.2.1: Pilot Bank Onboarding

Priority: HIGH Effort: 4 weeks Assignee: Implementation Team

Subtasks:

Acceptance Criteria:

  • Pilot bank selected and contracted

  • Requirements documented and approved

  • System customized for bank needs

  • Data migration completed successfully

  • UAT passed with sign-off

Task 4.2.2: Staff Training Program

Priority: HIGH Effort: 3 weeks Assignee: Training Team

Subtasks:

Acceptance Criteria:

  • Comprehensive training materials created

  • User manuals for all roles completed

  • Trainers certified on system

  • All users trained and certified

  • Training feedback incorporated

4.3 Go-Live Support

Task 4.3.1: Go-Live Preparation

Priority: HIGH Effort: 2 weeks Assignee: Implementation Team

Subtasks:

Acceptance Criteria:

  • All system tests passed

  • Go-live checklist completed

  • Support team ready and trained

  • Monitoring provides full visibility

  • Rollback procedures tested

Task 4.3.2: Post Go-Live Support

Priority: HIGH Effort: 4 weeks Assignee: Support Team

Subtasks:

Acceptance Criteria:

  • Support team available 24/7

  • System performance monitored continuously

  • Issues resolved within SLA

  • Feedback collected and analyzed

  • Critical fixes deployed quickly


Ongoing Maintenance Tasks

M1: System Monitoring & Maintenance

Task M1.1: Performance Monitoring

Priority: HIGH Frequency: Continuous Assignee: DevOps Team

Activities:

Success Metrics:

  • 99.9% system uptime

  • <2 second average response time

  • <0.1% transaction error rate

  • Database queries <100ms average

  • API calls <500ms average

Task M1.2: Security Monitoring

Priority: HIGH Frequency: Continuous Assignee: Security Team

Activities:

Success Metrics:

  • Zero successful security breaches

  • All patches applied within 48 hours

  • 100% audit log coverage

  • Monthly vulnerability scans clean

  • Quarterly access reviews completed

M2: Feature Enhancement & Updates

Task M2.1: Regular Feature Updates

Priority: MEDIUM Frequency: Monthly Assignee: Development Team

Activities:

Success Metrics:

  • Monthly feature releases

  • User satisfaction >90%

  • Feature adoption >80%

  • Performance improvements measurable

  • New reports meet business needs

Task M2.2: Regulatory Updates

Priority: HIGH Frequency: As Required Assignee: Compliance Team

Activities:

Success Metrics:

  • 100% regulatory compliance maintained

  • Updates implemented within deadlines

  • No compliance violations

  • Regulatory reports accurate

  • Audit findings addressed promptly


Resource Requirements

Development Team Structure

Core Development Team (8-10 people)

  • Technical Lead (1): Overall technical direction and architecture

  • Backend Developers (2): API development and database management

  • Frontend Developers (2): Web and mobile interface development

  • Mobile Developer (1): Native mobile app development

  • Integration Developer (1): External system integrations

  • DevOps Engineer (1): Infrastructure and deployment

  • QA Engineer (1): Testing and quality assurance

Specialized Support Team (4-6 people)

  • Security Specialist (1): Security audit and compliance

  • Database Administrator (1): Database optimization and management

  • UI/UX Designer (1): User interface and experience design

  • Business Analyst (1): Requirements and process analysis

  • Training Specialist (1): Documentation and training materials

  • Project Manager (1): Project coordination and management

Infrastructure Requirements

Development Environment

  • Development Servers: 4-6 cloud instances for development and testing

  • Staging Environment: Production-like environment for testing

  • CI/CD Pipeline: Automated build, test, and deployment pipeline

  • Code Repository: Git-based version control with backup

  • Project Management: Task tracking and collaboration tools

Production Environment

  • Application Servers: Load-balanced cluster with auto-scaling

  • Database Servers: High-availability PostgreSQL cluster

  • Load Balancers: Traffic distribution and SSL termination

  • Monitoring Systems: Comprehensive system and application monitoring

  • Backup Systems: Automated backup with offsite storage

Budget Estimates

Development Costs (12 months)

  • Personnel: $800,000 - $1,200,000

  • Infrastructure: $100,000 - $150,000

  • Software Licenses: $50,000 - $75,000

  • Third-party Services: $75,000 - $100,000

  • Training & Certification: $25,000 - $50,000

  • Contingency (20%): $210,000 - $315,000

  • Total: $1,260,000 - $1,890,000

Ongoing Operational Costs (Annual)

  • Personnel: $600,000 - $900,000

  • Infrastructure: $120,000 - $180,000

  • Software Licenses: $60,000 - $90,000

  • Third-party Services: $90,000 - $120,000

  • Support & Maintenance: $50,000 - $75,000

  • Total: $920,000 - $1,365,000


Risk Management

Technical Risks

Risk T1: Integration Complexity

Probability: Medium Impact: High Mitigation:

  • Start integration development early

  • Create comprehensive API documentation

  • Implement thorough testing protocols

  • Establish fallback procedures for integration failures

Risk T2: Performance Issues

Probability: Medium Impact: Medium Mitigation:

  • Conduct regular performance testing

  • Implement monitoring and alerting

  • Plan for horizontal scaling

  • Optimize database queries proactively

Risk T3: Security Vulnerabilities

Probability: Low Impact: High Mitigation:

  • Conduct regular security audits

  • Implement security best practices

  • Keep all dependencies updated

  • Establish incident response procedures

Business Risks

Risk B1: Regulatory Changes

Probability: Medium Impact: Medium Mitigation:

  • Monitor regulatory developments closely

  • Build flexible compliance framework

  • Maintain relationships with regulatory bodies

  • Plan for rapid compliance updates

Risk B2: Market Competition

Probability: High Impact: Medium Mitigation:

  • Focus on unique value propositions

  • Maintain competitive pricing

  • Emphasize superior customer service

  • Continuously innovate and improve

Risk B3: Customer Adoption

Probability: Medium Impact: High Mitigation:

  • Conduct thorough user testing

  • Provide comprehensive training

  • Implement gradual rollout strategy

  • Gather and act on user feedback

Operational Risks

Risk O1: Resource Availability

Probability: Medium Impact: Medium Mitigation:

  • Maintain adequate team size

  • Cross-train team members

  • Establish vendor relationships

  • Plan for staff augmentation

Risk O2: Infrastructure Failures

Probability: Low Impact: High Mitigation:

  • Implement redundant systems

  • Establish disaster recovery procedures

  • Conduct regular backup testing

  • Maintain 24/7 monitoring


Success Criteria

Technical Success Criteria

System Performance

  • Uptime: 99.9% system availability

  • Response Time: <2 seconds for 95% of transactions

  • Throughput: Support 1,000+ concurrent users

  • Error Rate: <0.1% transaction error rate

  • Security: Zero critical security vulnerabilities

Code Quality

  • Test Coverage: >90% automated test coverage

  • Documentation: 100% API documentation

  • Code Standards: All code passes quality checks

  • Security: Regular security audits with clean results

  • Performance: All performance benchmarks met

Business Success Criteria

Market Adoption

  • Customer Acquisition: 10+ financial institutions in first year

  • User Growth: 50% year-over-year growth

  • Transaction Volume: 100,000+ daily transactions

  • Customer Satisfaction: >90% satisfaction score

  • Feature Adoption: >80% feature utilization

Financial Success

  • Revenue Growth: 100% year-over-year revenue growth

  • Cost Efficiency: 50% reduction in operational costs for clients

  • ROI: Positive ROI for clients within 18 months

  • Market Share: 25% market share in Liberian banking technology

  • Profitability: Break-even within 24 months

Operational Success Criteria

Support & Maintenance

  • Support Response: <4 hours for critical issues

  • Issue Resolution: 95% of issues resolved within SLA

  • System Updates: Monthly feature releases

  • Training Effectiveness: 95% user certification rate

  • Documentation: Complete and up-to-date documentation

Compliance & Risk

  • Regulatory Compliance: 100% compliance with all regulations

  • Audit Results: Clean audit results with no major findings

  • Risk Management: All identified risks properly mitigated

  • Data Security: No data breaches or security incidents

  • Business Continuity: Disaster recovery tested and verified


Conclusion

This comprehensive task breakdown provides a roadmap for completing and deploying the RISWIS core banking system. The plan balances technical excellence with market needs, ensuring the system meets both functional requirements and business objectives.

The phased approach allows for:

  • Risk Mitigation: Early identification and resolution of issues

  • Iterative Improvement: Continuous feedback and enhancement

  • Market Validation: Pilot implementation before full deployment

  • Resource Optimization: Efficient use of development resources

  • Quality Assurance: Comprehensive testing and validation

Success depends on:

  • Strong Project Management: Clear coordination and communication

  • Technical Excellence: High-quality development and testing

  • User Focus: Continuous attention to user needs and feedback

  • Regulatory Compliance: Adherence to all applicable regulations

  • Market Awareness: Understanding of competitive landscape and customer needs

This plan positions RISWIS for successful market entry and long-term growth in the West African banking technology market.


Document Version Control

  • Version 1.0: Initial comprehensive task breakdown

  • Last Updated: January 2025

  • Next Review: Monthly during implementation

  • Stakeholders: Development Team, Project Management, Business Development

Last updated